Su Xiashan asked: "Manager Song, have you asked Mr. Zhao to urge the money to come and you can move?"
Song Xiaoshan explained: "Mr. Su, there are always some misunderstandings between Party A and Party B when doing engineering."
Su Xiashan smiled and said, "Manager Song might as well speak."
"good.
Party A often thinks about it today and lets us move tomorrow.
Some things cannot be done.
For example:
The exterior tiles of the landscape wall that were only confirmed today were covered with 20mm thick Chinese red granite.
Then I asked that this is only 5 square meters of small matter, a large unit of such a big one, will paste the granite tomorrow.
As a vulnerable group, our construction unit generally agrees to be good and good.
As a result, the second day, third day, fourth day, or even fifth day have not been posted yet.
This will cause Party A to be even more incomprehensible about our construction unit.”
"Yes, I am Party A now and I don't understand.
Can't you handle such a small thing?"
"Mr. Su, these things depend on luck."
"Manager Song will explain in detail. I'm a little confused when you say that."
"There are several possibilities for Party A to ask for a 20mm thick Chinese red granite the next day.
The first one is the most satisfactory result for your Party A.
There was just 20mm thick Chinese red granite material on site, and there were workers, so the task was easily completed.”
"Yes, we are the favorite of Party A."
"You won't like the second one after that.
The second type is that there is exactly 20mm thick Chinese red granite material on site, but there are no technical workers who lay it out, which will lead to the failure of the task."
"Yes, this is a possibility, but you can look for this again. If you don't have it in the morning, just come in the afternoon."
"You don't understand this very well. If no one comes in the morning, we will basically not come in the afternoon. Otherwise, if we come, we will still have a salary of one day. Then we will only lay the 5 square meters of granite.
Isn’t that a terrible loss?”
"Yes, yes, yes, you'll continue to talk about what other possibilities are there."
"The third type is that there is no 20mm thick Chinese red granite material on site, so you need to purchase it. Sometimes you are lucky in the nearby market, so it will take a day or two to complete it."
"right."
"The fourth type is that there is no 20mm thick Chinese red granite material on site, so you need to purchase it. If you are not lucky, there are no nearby markets. You need to order in other markets or mines? In this way, it often takes more than a week."
"Yes, it will be troublesome if you encounter this situation."
"So, Mr. Su, although our construction unit wants to do some project? We have a good time, we are extremely reluctant to do work.
Because whether the rush to work can be completed on time is too many factors affected by the external affairs office.
Even windy and rainy may affect our material supply? Impact the speed of our on-site construction.”
"Um."
"Mr. Su, if we want to truly complete this project, it must be based on the current plan? According to the opinions of our masters, we can confirm various materials and samples as soon as possible. Only then can we get faster.
”
"I can't make the decision on this? I just can help with the price, contract signing, payment, settlement and other work. For the confirmation of the sample, you still have to find our on-site manager Liu Yuze."
“Yes? Mr. Su.
What about this after saying this? I will just talk to you.
Your Liu Yuze and Liu Gong are quite slow in confirming the samples. We have handed over the samples for more than a week? We haven't decided yet.
For these factors, even if we have money, we don’t know what to buy.
When you have time, or when it is convenient, can you also help us communicate with Mr. Liu? Let him know this? Once he delays confirming the sample, our project progress will definitely be naturally delayed."
"It's okay to tell you something, but if you confirm, you still have to ask him to confirm, otherwise the management will be in chaos."
"This one can be found, thank you, Gong Su, I'll give you a cup."
"Drinke together."
Su Xiashan asked again: "Is the current situation of your project department? The samples have not been confirmed and the money has not been in place, so things cannot be started?"
Song Xiaoshan replied helplessly: "It tastes a bit like this."
Su Xiashan said to Zhao Manfu: "Mr. Zhao, if you have this nine million supplementary contract now, you will not be able to start construction after more than a week.
Although Manager Song explained it to me just now, I also expressed my understanding.
However, while communicating with relevant leaders of the company, I still heard some gossip.
Many leaders complained about our Mr. Tang Zhiqiang and Mr. Tang, saying that he did not have the ability to identify the team and had to bite the bullet and designate you to become a construction unit.
If this adverse effect is not smoothly eliminated.
First of all, it is difficult to approve the progress payment of your supplementary contract, and it will be difficult to approve the settlement in the future.
If I want to do the second phase of Bowan, I think I hope it will become very slim."
Zhao Manfu's face also looked ugly, and he slowly said word by word: "Then, Mr. Su, do you have any good suggestions?"
Su Xiashan replied: "There is a suggestion, but you are currently facing so many difficulties. Can you continue to implement it?"
Zhao Manfu agreed confidently: "As long as there is a temporary solution, I am willing to try it out.
Please give me advice.”
Su Xiashan replied: "I dare not give advice, I am so serious.
There are some suggestions.
My understanding is that some of our leaders on Party A are actually looking at some appearances, not seeing the essential problems, or they don’t understand them themselves, or they understand them themselves, but they just want to cause trouble for us.
So, no matter what others think.
My understanding is that as long as the construction on the project department is activated, whether it is really moving is not that important.
At least this can block others' mouths for a while. In this period of time you can handle the conditions that must be met for construction, and you will naturally be able to overcome the current difficulties."
After hearing this, Zhao Manfu's eyes lit up: "I understand Mr. Su's suggestion. Manager Song, do you understand? Do you know how to solve it?"
Song Xiaoshan replied: "Our company controls costs very strictly. If some workers do some useless work, it seems to pass the test on the surface, but in fact it is a waste of money and it is difficult to reimburse.
And if you want to do this, you need work support from your department, Mr. Zhang."
Zhang Yunqing: "I clearly support it, but the project department needs to use its brains to try to be as good as possible."